Run the Schedule Yourself.
A working CPM scheduler in your browser. Change a duration or a relationship and the dates, float and critical path recalculate instantly, the way they do in professional scheduling software.
Change names, durations, calendars and predecessors. Type logic as A1010, A1020SS+5 or A4040FF.
Freeze today's plan, then slip an activity. The variance column shows what moved and by how much.
Red bars have no float. Thin lines after a bar show float. Click any bar or row to see its drivers.
The side panel screens your logic for open ends, lags, constraints and float, like a formal health check.
| Activity ID | Activity name | Cal | Dur | Start | Finish | Total float | Free float | Predecessors | BL finish | Var |
|---|
Your schedule is saved in this browser only. Nothing is uploaded. This sandbox is for learning and exploring; real project schedules belong in your scheduling platform, reviewed by an experienced scheduler.
Five minutes that explain the critical path.
Slip the switchgear
Set a baseline, select A2010 and press +5 days four times. Watch ready for service move day for day, because switchgear sits on the critical path.
Use the float
Now delay A2030, the chillers. Nothing moves until its float is consumed, then a new critical path appears.
Overlap the work
Change A4040's logic from FS to SS with a lag and see how much time overlap recovers, and what risk it adds.